Team Plan 2006-07

Primary Role: Strategic aim is to enable people to stay in their own homes. Clients are people with acquired physical disabilities who have long term chronic conditions such as Multiple Sclerosis, Stroke and Head injury. Clients may also have some other psychosocial issues such as depression, carer under stress etc. We provide a wide range of rehabilitative, therapeutic and social supports in both centre and community settings.

 

PlanImage1

 

Operations
Key Objectives Key Tasks/Timescales Monitoring Methods
Develop/pilot more flexible activity programme model Design and implement new model - Oct 06 Ongoing feedback from staff and clients - final evaluation in June 07
Continue development of community rehab model Community rehab goal for individual clients identified, input given then monitor. Oct 06 on Numbers of clients achieving goal.
Pilot local area co-ordinator model in one local area Initial pilot by Jan 07 No. of clients achieving community connection
Further develop satellite group activity model Ongoing development. Aim to have 2nd self-financing group by June 07. Explore options for 3rd group 2nd group becomes self-financing infrastructure for 3rd group
Pilot evening activity project in conjunction with vol org Initial plan by Jan 07 Setting up of group
Pilot/study physiotherapy needs of clients -MS -Stroke Setup studies by Jan 07 Measure results of pilot (before/after) produce report
Develop "sth Edinburgh partnership" voluntary organisation. Strengthen organisation Attract funding for projects eg advocacy, therapy etc Expansion of oragnisations role
Policy
Key Objectives Key Tasks/Timescales Monitoring Methods
Review of the role of centre/aims and objectives. Includes defintion of therapeutic, rehabilitation and respite models/packages Major staff event - Dec 06. Possibly followed by further events involving clients carers Date set and event run
Develop Centre role in relation to and contribute to pan Lothian strategy. Includes liaison with MCNs and pilot projects. Pilot projects with MSNs (see opeations) Defined our role in relation to therapeutic and rehabilitative models -07 on Definition or roles Acknowledgement in MCN structure
Explore dependency models with a view to developing measurable inputs for specific clients Develop system (based on assessment/need) to link staff input to needs of clients Jan 07 on Development of system to be piloted/implemented
Administration
Key Objectives Key Tasks/Timescales Monitoring Methods
Have comprehensive risk assessments in place for all aspects of Centre

- general risk assessments
- room risk assessments
- fire risk assessments
- individual risk assessments

by Nov 06

Completion of risk assessment system - ongoing monitoring
Participate in "best value" exercise which involves benchmarking our service against other similar ones participate in process, focus groups, questionaires etc by Dec 06

Completion of process

Completion of report

Continued development of Personal Plan for clients plus Effective review system complete 6th version of personal plan - Dec 06 reviews ongoing Completion of 6th version. Each client to be reviewed
Explore "direct referrals" Liase with practive teams Dec 06. Meeting with finance by Jan 07 Accuracy of oracle printouts
Resolve budget discrepancies, ensure accuracy of Oracle budget management system Meetings with finance
By Jan 07
Accuracy of Oracle printouts
Encourage uptake of ILF/Direct payments when appropriate. Identify appropriate clients Liase with relevant agencies. Ongoing Measure of number of clients taking up this option
Building
Key Objectives Key Tasks/Timescales Monitoring Methods
Improve access path to garden Army to undertake as community project - Oct 06 Task completion
Develop new activity room (from old woodwork room) Staff/volunteers to redevelop - Nov 06 Task completion
Attract additional funding for garden project Design project to attract funding - Jan 07 Project in place
Further develop coffee bar. Link to health living Strategy to link coffee bar to healthy living agenda Nov 06 Strategy in place and implemented
Change structure re cleaners Explore options New structure in place

Apply pressure on dept for - Roof replacement (sth side)
- Effective fire system eg.
automatic doors, improved alarm system, sprinklers?

Ensure property reps are aware of issues ongoing Task completion
Management
Key Objectives Key Tasks/Timescales Monitoring Methods
Implement PRD staff supervision system All staff to have initial meeting by Dec 06 Evidence of meetings and regular supervision
Carry out Training Needs Analysis for all staff Organise event following "centre role" event - spring 07 Each member of staff to have printed plan
Persue "restructure of management" for disability services-area co-ordinator model Resurrect model with line managers - November 06 Passed up the line (again) to senior management
Pilot -PA supervision/support system Identify scale of gap. Provide supervision for PA - Oct 06 Measure success of intervention

 